Dry set the shower basin, 'cept for 12 accent tiles. David installed and stained the last wall panel, stained the last built-in.

Tomorrow, will set the shower basin, install baseboards in closet, paint touch-ups. Also tomorrow, tile company will come out to measure for the shower door - another item I decided not to bother with myself...

A different type of milestone tomorrow for David - 100 days (calendar days). So David's at 937 hours, 100 days = 9.37 hrs/day ~ 65 hours per week. I'm at 760 hours, 127 days = 5.98 hrs/day ~ 42 hours per week (plus 40 hours at actual regular job, of course, I'm no slacker).

Also spoke to the county building inspector today - in their words, they are not the "furniture police" so I do plan to move in BEFORE inspection. They want inspection before we're living in the house - so we'll move the PODs into the house, then install banisters, inspection, and then move Jen and kids from Aunt Becky's into the house. Interesting that carpet is not needed for inspection... 'course, it is needed for move-in... so... whatever...

No comments:

Post a Comment