First Revised Remediation Schedule

No glued board, a couple of minor surprises, nothing major - a week ahead of the baseline schedule.  This is the first update.  The end date didn't move, but most major operations have moved up about a week...  stay tuned...

[Note dated 11/1/2010 - this schedule is as of May 26 - actual completion, as you can read, was in October - we ran about 3 weeks over schedule, roughly]


Click on this image for a larger view.