David made great progress on the closet built-in. Also set tile in the shower nooks. Only the border (need more bullnose), basin, and 2/3 of the tub backsplash to set. David grouting shower walls tomorrow, I'll try to get the tub backsplash set.Al was by yesterday (I stayed with Jen and the kids, blogspot doesn't work on Jen's computer), coated the floor. Looks great. Was supposed to be by today, another no-show... promises to be by tomorrow for the last coat. Moving in and out of the house by extension ladder to the second floor... not cool. If by tomorrow, will be able to walk on it on Saturday, furniture on Sunday.
Have our first meeting with our attorney tomorrow. I guess the beginning of the next phase of this ordeal.
David is 1 hr 40 minutes from 900 hours... I'm at 735.