Master, Closets


Good day. Set tub tile, dry-set 80% of the bathroom floor. David observed a "design flaw" in the tile - with accent tiles arranged in the floor at every 4th corner... there is not a single tile in the floor that doesn't have a cut. I didn't realize this until I was into it... so it took a little longer than I thought... should have it set tomorrow anyway...

Thanks to David - worked my closet most of the day - laid the hardwood floor and painted the walls (not in that order). Then went to work in the kids' bath - still need shoe molding in before toilet - he's motivated to get the toilet in tomorrow.

Thanks to JP for coming over today - installed shelves and rods in Abby's, Will's, Guest, and half of Jen's closet. Also cut the drawer bases for the built-ins, and painted them. A big help today.

A couple of milestones coming up - David will crack 800 tomorrow, I'm a couple days away from 700. The project cracked 2,400 hours today. That's about 1 hour for every square foot - if anyone cares about metrics... doesn't seem like a lot when you put it that way...

Tomorrow, more tile, more hardwood, more kid's bathroom.