Sunday, September 26, 2010

Ready for Carpet

Tile in master bath grouted; downstairs toilet installed, everything cleaned. We are ready for carpet. What remains...

- Speakers (dining, master)
- Volume controls
- Security system (2 keypads, 1 heat/smoke, 1 siren)
- Painting/caulking the built-in drawers
- Doors to the built-ins
- Putty and touch up shoe
- Shoe molding in master bath
- Access door to tub in master bath (plug in tub)
- Seal grout, master bath
- Banister
- Curtain rods in living
- Shoe around kitchen cabinets
- Door knobs in exterior doors
- Mirror, towel ring, paper holder in downstairs bath
- Install shower fixtures in master

- Install shower door in master (hired-out; Thursday)
- Carpeting (hired-out, Monday)

So... aside from the banister, I don't consider any of these to be big chores for us; and aside from the banister and maybe speakers due to delivery schedule, I think we can get all of this done by end of day Tuesday...

Unbelievable that it is all wrapping up...

I'll hit 800 hours tomorrow; David will hit 1,000 on Tuesday (probably).