Good progress today. More scrap-up this weekend. Big news - fiberglass scheduled to arrive on 6/11. I think this will be pretty good timing - we're continuing to make great progress.
Other big news, finally finished logging all of the removed drywall. If you've ever talked to me about it - I'd usually estimate 70% of the drywall was Chinese; I must know what I'm talking about because here's the count:
Chinese Drywall Proved by Stamp 130
Chinese Drywall Proved by End-Tape 90
Unmarked - Suspected Chinese Drywall 103
Domestic Drywall Proved by Stamp 83
Domestic Drywall Proved by End-Tape 28
Unmarked - Suspected Domestic Drywall 15
Unknown (missing data) 18
323 pieces of Chinese drywall of the 467 that we removed, by count: 69.2%.
Today: 0%