Mom and Dad left today - thanks for all of the help.
David worked the built-in more - last sheet of MDF cut - will need more. Tile in the laundry room and kids bathroom is finished - looks awesome - thanks Dave.
I installed a light, and did some paperwork.
Getting close. Major remaining items, in sort of an order:
- Built-ins - I hope to have done this weekend
- Plumbing - sweat on valves, install kids' bathtub fixtures
- One more kitchen cabinet
- Closets - shelves, my closet, rods, pantry
- Stairs - parts arriving next week
- Master Bath - tile the hell out of it... Jen to pick out tile
- Master Bath - cabinets, fixtures, plumbing
- Kids bath - paneling, trim, cabinets
- Re-finish hardwood - hire out, out of house 3-5 days
- Install downstairs bath sink and faucet
- Wallpaper
- Carpet